An intersection in Knoxville will be closed beginning Monday for construction. According to Public Works Director, Jeff May pavement on the intersection of South Fifth Street and Montgomery Street will be removed and replaced beginning Monday, if weather permits. May says the intersection was poured last fall as part of the South Fifth Street Project, but was not construction in accordance with the specifications and will be replaced at the Contractor’s expense. The replacement work is expected to take approximately one week to complete.