streetscape-perspective

The Indianola Downtown Square Reconstruction Project worked on curb and gutters on Salem Ave between Buxton and Howard last week, in addition to the construction of sidewalk ramps at the intersection of Salem and B Street. This week, curb and gutter placement will take place on Buxton Street, and preparation work for the placement of permeable pavers will begin. Additionally, it is anticipated that the Intersection of B Street and Salem will be reopened to traffic next week. Phase 1 construction is expected to be completed by mid-November.