Construction on the Indianola Square Reconstruction Project recently worked on storm sewer repair on Buxton St. south of Salem Ave, permeable paver installation, and electrical conduits being placed behind the back of the curb. This week, permeable paver installation will wrap up, paving will take on Buxton Street south of Salem Avenue, the paving of the intersection of Buxton Street and Salem Avenue will take place, electrical work will continue on Phase 1, and a few areas of sidewalk construction will begin. As the street portion concludes, sidewalk work begins, and pedestrians and commuters in the area should be aware of short-term sidewalk closures and pedestrian detours. Phase 1 of the project is expected to be complete by mid-November.