Work continues on the VA project in Knoxville. Work on the southside had stopped due to a previously unknown tunnel they found that contained asbestos. The asbestos has been removed and work will shift back to the southside. The abatement process on the final buildings is almost complete and those buildings should be taken down in the next 25-30 days. Dirt work has also begun and will continue as crews put the dirt back to make sure the area can be developed.