20220629_151319

Work continued on the Indianola Square Reconstruction Project this week, which included the removal of the road on Ashland Ave between 1st and Howard and the installation of the pedestrian fence. Installation of the sidewalk, planter beds, and seat walls began on the west side of Howard, while sidewalk work began on the east side of Howard. Salem Ave was also opened to traffic.

Over the course of next week, sidewalk work will continue on Howard with the goal of reopening the street on July 14th, and subgrade prep work, install rock chambers, and subdrain work on Ashland will continue.