Work continued on the Indianola Downtown Square Reconstruction Project over the past week, as paving work on Ashland Ave progressed. Stormwater installation on Ashland between Howard and Buxton is complete, the curbs and road is being replaced on Ashland between 1st St and Howard, and the paving on Ashland/Howard intersection has begun.

Over the next week, the removal and replacement of the sidewalks on Ashland between 1st and Howard will begin, which will not impact businesses. Pavers will be placed on Ashland, storm sewer work will begin, and the installation of rock chambers and subdrains on Ashland between Howard and Buxton will continue.