Work on the downtown Indianola Square Reconstruction Project continued over the last week, which included the completion of the Ashland and Buxton intersection, and all roadway paving on the project is now done. Permeable pavers have been installed on Ashland between Buxton and B Street, planter beds were installed on the north side of the mid-block of Ashland, and all crosswalks are now complete.

Over the next week, the installation of sidewalks and decorative items on the west end of Ashland will begin, and goals set for the end of the month include the completion of the installation of electrical and street light poles, street markings on the mid & west side of Ashland, and all signs installed.