The vast majority of power lines that can go underground are currently in that state in the City of Pella. At Tuesday’s Pella City Council meeting, a public hearing will be held to get some of the last overhead lines converted in the community. The council will review two bids for a project to install underground conduit, box pads, and pull boxes for the electrical distribution system from Idaho Drive at the water treatment plant to the clear wells downstream at Howell Station Campground. The city’s electric distribution crew would follow up with installation of the cable and transformers. The project is estimated to cost $700,000 and would be completed by June 30th, 2024. This week’s Pella City Council meeting begins at 6 p.m. Tuesday in the Pella Public Safety Complex.