Interior work on the new clubhouse at Westwood Golf Course in Newton is expected to begin the week of November 25th. Newton City Staff says that will cause a two week change in entering and parking at the city owned facility. A portion of the west end parking lot will be used for storage, and the entrance road along the north side of the lot will be closed. City staff says visitors should enter the golf course via the east side of the parking lot, which is usually for exit only. On Wednesday, November 6th, a pre-construction meeting for the interior phase of the project was held. City staff expects the 60’ x 100’ post-frame clubhouse with exterior steel will be ready for use by the end of March.