Work continues at the indoor aquatic center in Pella.
At this week’s city council meeting members approved more than $60,000 in change orders for the project. City Finance Director Corey Goodenow says it was a challenge to remodel the building because of when it was built and the stress a pool has on a facility. Aquatic Center Manager Mallary Herring says crews are finishing up the exterior work and will soon shift their focus indoors. The project is expected to be finished in November.