Work on the Indianola Downtown Square Reconstruction Project is nearing completion, with work on Ashland Ave continuing.

The sidewalk path is finished on the mid-block of Ashland, while sidewalk removal/installation on the west block of Ashland and permeable paver installation are completed. Over the next week, plantings, electrical week, street striping, and signage are all planned to be completed.

Through October, all concrete work will be completed and all roads will be completed and open to traffic, with a goal of being significantly done with the project by October 31st.